MED Estimate - Likely Generation Build Proposals |
|
|||
Year |
Owners/Operators |
Location |
Fuel Type |
MW |
2003 |
Mighty River Power |
Rotokawa (expansion) |
Geothermal |
6 |
2004 |
Meridian Energy |
Manapouri Efficiency Improvements |
Hydro |
30 |
2004 |
TrustPower |
Tararua |
Wind |
36 |
2004 |
Contact Energy |
Otahuhu or Whirinaki |
Distillate |
150-192 |
|
|
|
|
|
2004 |
Confidential |
Various Projects |
Geothermal |
22 total |
|
|
|
|
|
2005 |
Meridian Energy |
Manapouri Efficiency Improvements |
Hydro |
20 |
2005 |
Genesis Energy |
Hau Nui |
Wind |
8 |
2005 |
Tuaropaki Group |
Mokai (expansion) |
Geothermal |
39 |
2005
|
Meridian Energy
|
Manawatu
|
Wind
|
83-96
|
2005 |
Confidential |
Various Projects |
Geothermal / Wind |
43 total |
|
|
|
|
|
2006 |
Genesis Energy |
Huntly - e3p |
Gas (CCGT) |
360-400 |
2006 |
Putauaki Trust |
Kawerau |
Geothermal |
50 |
2006 |
Contact Energy |
Tauhara |
Geothermal |
15 |
2006 |
Contact Energy |
Poihipi Road (Steamfield) |
Geothermal |
20 |
2006 |
Top Energy |
Ngawha II |
Geothermal |
20 |
|
|
|
|
|
2006 |
Confidential |
Various Projects |
Geothermal / Hydro |
30 total |
|
|
|
|
|
2007 |
Confidential |
Various Projects |
|
440 total |
|
|
including coal, geothermal, hydro, |
|
|
|
|
hydro-irrigation and wind |
|
|
|
|
|
|
|
2008 |
Meridian Energy |
Project Aqua - Stage 1 |
Hydro |
285 |
|
|
|
|
|
2008 |
Confidential |
Various Projects |
Gas Cogen / Hydro / |
122 total |
|
|
|
Geothermal |
|
|
|
|
|
|
2009 |
TrustPower |
Wairau (Marlborough) |
Hydro-Irrigation |
115 |
|
|
|
|
|
2011 |
Confidential |
|
Geothermal |
50 |
2012 |
Meridian Energy |
Project Aqua - Stage 2 |
Hydro |
285 |
|
|
|
|
|
2012 |
Confidential |
|
Hydro |
80 |
|
|
|
|
|
Notes: |
|
|
||
Some options have not been included in this table because they are mutually exclusive to those shown. Not all these options will progress to development, and some timings for development are estimated. The Year refers to the year in which the plant would be available for winter generation. This list represents data available at 8/5/03 and is subject to ongoing change. |
||||
|
|
A4108 (2R) 3 LEGISLATIVE FISCAL ESTIMATE [SECOND REPRINT] ASSEMBLY
ADDITIONAL FILE 4 – ESTIMATED PATSER ERROR RATE FOR
AEAT 5231 ISSUE 2 ESTIMATED BENZENE CONCENTRATIONS IN
Tags: build proposals, likely, generation, ownersoperators, build, estimate, proposals