Town of Buckland
Highway Department
Yearly Planner
2020
Weather emergency response 5 crew
Snow removal 4 weeks 2-5 crew
Road surface, drainage maintenance 1-2 weeks 1-5 crew
Roadside tree limbing/removal 4 weeks 2-5 crew
Equipment maintenance/repair 1-2 crew
Cold patch town wide 1-4 weeks 1-5 crew
Weather emergency response 5 crew
Snow removal 4 weeks 2-5 crew
Road surface, drainage maintenance 1-2 weeks 1-4 crew
Roadside tree limbing/removal 4 weeks 2-5 crew
Equipment maintenance and repair 1-2 crew
Cold patch town wide 1-4 1-5 crew
Begin move to new garage 1-5 crew
Weather emergency response 4 crew
Snow removal 4 weeks 2-5 crew
Sidewalk sweeping 1-4 days 1-2 crew
Street/Road sweeping 8-10 weeks 2-3 crew
Road surface, drainage maintenance 1-2 weeks 2-4 crew
Roadside tree limbing/removal 4 weeks 2-4 crew
Equipment maintenance and repair 1-2 crew
Cold patch town wide 1-4 1-4 crew
Move/set up new garage 1-4 crew
Weather emergency response 4 crew
William St. II C.D.B.G 4-8 weeks 1 crew
Sidewalk sweeping 1-4 days 1-2 crew
Street/road sweeping 2-4 weeks 2-3 crew
Culverts/water way clearing 2-3 weeks 2-4 crew
Cold Patch town wide 1-2 weeks 1-4 crew
Inspect and ready summer equipment 1 week 1-2 crew
Spring inspection of roads/streets 1 week 1 crew
Move/set up new garage 1-4 crew
May
Street/road sweeping 2-4 weeks 2-3 crew
William St. II C.D.B.G. 1 crew
Reshape/Ditch dirt roads 2-3 weeks 3 crew
Prepare Upper Street (Memorial Day parade route) 1-2 weeks 4 crew
Winter equipment repair/storage 1 week 1-2 crew
Pavement marking 1 day 1 crew
Prepare 7 roads for o/s 1-2 weeks 2-4 crew
Clean out culverts and waterways 1-2 weeks 2-4 crew
Vehicle Inspection 1-3 days 1 crew
Transfer station erosion repair 1 week 1-4 crew
Cold/hot patch town wide 1-4 weeks 1-4 crew
Set up new garage 1-4 crew
Cold/Hot patching 1-3 weeks 1-4 crew
Oil/Stone Roads 1 week 1 crew
Reshape/ditch Gravel roads 1-4 weeks 4 crew
Clean out culverts and waterways 2-3 weeks 2 crew
Prepare 7 roads for o/s 2 weeks 3-4 crew
William St. II C.D.BG 1 crew
Transfer station erosion repair 1 week 1-4 crew
Culvert/waterway cleaning 1-2 weeks 2-4 crew
Reshape/ditch Gravel roads 1-3 weeks 2-4 crew
Cold/Hot Patch 1-4 weeks 1-4 crew
Catch Basin/lateral jetting 1 week 1 crew
William ST. II C.D.B.G 1 crew
Roadside mowing 4 (+-) weeks Contracted
Repair 1 catch basin Birch RD. 1-2 days 2-3 crew
Oil/Stone 7 Roads 1 week 1 crew
Oil and Stone Roads 1 week 1 crew
Cold/ Hot patch 1-4 weeks 4 crew
Sweep excess stone 1-2 weeks 2-3 crew
Roadside tree limbing, edge/ditch 1-2 weeks 3-4 crew
Roadside mowing 4 (+-) weeks Contracted
Roadside tree limbing and removal, edge/ditch 4 weeks 3-4 crew
Dirt road repair/winter preparation 1-4 weeks 2-4 crew
Sweep excess stone 1 week 2 crew
Hot/cold patch town wide 1-4 weeks 1-4 crew
Dirt road repair/winter preparation 2-3 weeks 2-4 crew
Roadside tree limbing and removal, edge/ditch 1-3 weeks 3-4 crew
Inspect and prepare winter equipment 1 week 1-2 crew
Hot/cold patch town wide 1-4 weeks 1-4 crew
Plant whips @ drainage, road edges, and hazards 1-4 weeks 1-4 crew
November
Install winter equipment 1 week 1-4 crew
Plant whips @ drainage, road edges, and hazards 2-3 weeks 2 crew
Clean, dig out sumps for culverts, clear waterways 2-3 weeks 2 crew
Weather emergency response 4 crew
C.B. Rd. repair 1 crew
Weather emergency response 4 crew
Snow removal 4 weeks 2-3 crew
Road surface, drainage maintenance 1-2 weeks 1-4 crew
Roadside tree limbing and removal 4 weeks 2-4 crew
Cold patch town wide 1-2 weeks 1-4 crew
Town Rubbish – 1-2 times weekly 2 hours 1-2 crew
-Highway garage, town hall, police department, Village Square.
Wind, rain, snow, and ice emergencies and resulting damage affect schedule.
Crew Attendance affects schedule, i.e., sick time, personal time, injury, vacation, Highway position Vacancies. Vacation time is discouraged from December 1 through April 1. Crew members take anywhere from two to six weeks vacation time each during the spring, summer and fall months (up to 15 weeks the highway department operates with less than a full crew).
Unexpected circumstances requiring immediate attention affect schedule as well.
COVID-19