Project Procurement Plan
47817
Namibian Coast Conservation and Management Project
(Grant No. TF 055983)
Simplified Procurement Plan
1. Project information: Namibia, Namibian Coast Conservation and Management Project, P070885.
Project Implementing Agencies: Ministry of Environment and Tourism (MET) and Ministry of Regional and Local Government, Housing and Rural Development (MRLGHRD)
2. Bank’s approval Date of the procurement Plan: June 2005
3. Date of General Procurement Notice: June, 2005
4. Period covered by this procurement plan: February 2009 to September 2010
Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.]
|
Procurement Method |
Prior Review Threshold |
Comments |
1. |
ICB and LIB (Goods) |
> = US$ 100,000.00 |
All contract are Subject to Prior Review |
2. |
NCB (Goods) |
< US$ 100,000.00 |
First contract is Subject to Prior Review |
3. |
Shopping |
< US$ 50,000.00 |
No contract is subject to prior review |
4. |
Direct contracting |
All values |
All contract are Subject to Prior Review |
5. |
IAPSO |
All values |
All contract are Subject to Prior Review |
2. Pre-qualification. There will be no prequalification of bidders.
3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A
Reference to (if any) Project Operational/Procurement Manual: The procurement procedures and Standard Bidding Documents (SBD) to be used for each procurement method, as well as model contracts for works and goods procured, are presented in the Project Implementation Manual which has been approved prior to Grant Agreement signing.
Any Other Special Procurement Arrangements: NONE
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Ref. No. |
Contract (Description) |
Estimated Cost |
Procurement Method |
Prequalification (yes/no) |
Domestic Preference (yes/no) |
Review by Bank (Prior / Post) |
Expected Bid-Opening Date |
Activity no |
1 |
Design and layout of the ICZM Bill |
2,500 |
Shopping |
No |
Yes |
Post |
Sept 2010 |
I.1.5.a |
2. |
Editing of the ICZM Bill |
2,500 |
Shopping |
No |
Yes |
Post |
Sept 2010 |
I.1.5.a |
3 |
Printing of the ICZM Bill |
5,000 |
Shopping |
No |
Yes |
Post |
Sept 2010 |
I.1.5.a |
4 |
Printing of the Green Paper Document |
25,000 |
Shopping |
No |
Yes |
Post |
March 2009 |
I.3.1 |
5 |
Design and Layout of the Green Paper |
15,000 |
Shopping |
No |
Yes |
Post |
March 2009 |
I.3.1 |
6 |
Printing of the NACOWP document |
10,000 |
Shopping |
No |
Yes |
Post |
Sept 2010 |
I.3.5 |
7 |
Design and Layout of the NACOWP document |
30,000 |
Shopping |
No |
Yes |
Post |
Sept 2010 |
I.3.5 |
8 |
Purchase of Computer for MET coastal offices |
15,000 |
Shopping |
No |
Yes |
Post |
March 2009 |
II.2.2 |
9 |
Printing of the Coastal Biodiversity Status Report |
12,000 |
Shopping |
No |
Yes |
Post |
March 2010 |
II.2.3 |
10 |
Printing of Coastal Awareness Booklets |
7,000 |
Shopping |
No |
Yes |
Post |
March 2009 |
II.3.2.d |
11 |
Design and Layout of the Coastal Awareness Booklets |
3,000 |
Shopping |
No |
Yes |
Post |
March 2009 |
II.3.2.d |
12 |
Printing of the National Coastal Profiles |
20,000 |
Shopping |
No |
Yes |
Post |
Nov 2009 |
II.3.3 |
13 |
Printing of the PA’s and related regulations report |
30,000 |
Shopping |
No |
Yes |
Post |
August 2009 |
III.1.2 |
14 |
|
|
|
|
|
|
|
|
Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
|
Selection Method |
Prior Review Threshold |
Comments |
1. Firm’s |
QCBS |
>=US$ 100,000.00 |
All contract are Subject to Prior Review |
Consultant Qualification Selection (CQS) |
< US$ 100,000.00 |
No contract is subject to prior review |
|
Least Cost Selection (LC) |
< US$ 100,000.00 |
No contract is subject to prior review |
|
2. Individuals |
Individual Consultant (IC) |
>= US$ 50,000.00 |
All contract are Subject to Prior Review |
Individual Consultant (IC) |
< US$ 50,000.00 |
No contract is subject to prior review |
|
Single Source Methods |
All values |
All contract are Subject to Prior Review |
2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 100,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: None
4. Consultancy Assignments with Selection Methods and Time Schedule
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Ref. No. |
Description of Assignment |
Estimated Cost |
Selection Method |
Review by Bank (Prior / Post) |
Expected Proposals Submission Date |
Activity no. |
15 |
Development of an income/revenue strategy for the coastal Protected areas |
30,000 |
IC |
Post |
30 July 2009 |
I.1.4 |
16 |
Development of the ICZM Bill |
72,000 |
CQS |
Post |
31 January 2010 |
I.1.5 |
17 |
Organise the High Level workshop |
20,000 |
IC |
Post |
31 March 2009 |
I.2.2 |
18 |
Development of the institutional arrangements report form the implementation of the coastal policy |
30,000. |
CQS |
Post |
28 February 2010 |
I.4.1 |
19 |
Assess the implementation of the training strategy and recommendation provide further training |
20,000 |
CQS |
Post |
31 July 2010 |
II.1.9 |
20 |
Organisation of a Study Tour |
10,000 |
IC |
Post |
31 June 2009 |
II.1.10 |
21 |
Develop a study to define the future ICZM roles and functions |
15,000 |
IC |
Post |
31 June 2009 |
II.1.11 |
22 |
Identify a cost effective collection of coastal and Marine Biodiversity data. |
27,000 |
CQS |
Post |
31June 2009 |
II.2.1 |
23 |
Implement the agreed cost effective collection and sharing mechanism of coastal and Marine Biodiversity data. |
40,000 |
CQS |
Post |
31 Dec 2009 |
II.2.2 |
24 |
Compile a coastal and Marine Biodiversity data status report and develop M&E tool for assessing of status |
32,000 |
CQS |
Post |
31 June 2009 |
II.2.3 |
25 |
Maintenance of the NACOMA webpage |
10,000 |
IC |
Post |
13 July 2008 |
II.3.2.c |
26 |
Identify and develop Coastodians awareness campaign activities and coordinates its implementation |
10,000 |
IC |
Post |
29 April 2009 |
II.3.2.e |
27 |
Develop a user friendly DVD compiling of all NACOMA products and other relevant coastal and marine data. |
20,000 |
CQS |
Post |
29 February 2010 |
II.3.4 |
28 |
Support Coastal local authority to develop an environmental policy and management plans |
30,000 |
CQS |
Post |
30 June 2009 |
III.1.12 |
29 |
Support the development of regulation of policies on ICZM implementation. |
40,000 |
CQS |
Post |
30 Sept 2009 |
III.2.4 |
1. In this section the agreed Training and Workshops Activities are listed with time schedule
No. |
Expected outcome / Activity Description |
Estimated Cost |
Start Date |
End Date |
Activity no. |
30 |
Workshops to support the Government to formally agree on the institutional mechanism and arrange for the implementation of the coastal policy |
25,000 |
01 June 2009 |
31 Nov. 2009 |
I.2.2 |
31 |
Workshop to identify and agree on an cost-effective mechanism to operationalise, integrated and improve accessibility and usage of data for coastal and marine biodiversity information |
5,000 |
01 Sept 2009 |
31 Dec 2009 |
II.2.1 |
CHOOSES A COLLEGE PROJECT RUBRIC (FILL IN
REVISION CONTROL INFORMATION PROJECTSHSISCVSUTILITIESARRAYARRAYDOCV
14 NOVEMBER 2005 PATRINA BUCHANAN PROJECT MANAGER INTERNATIONAL
Tags: 47817 namibian, 47817, management, conservation, procurement, namibian, coast, project