ANNEX 2 - PROCUREMENT PLAN TEMPLATE FOR CONSULTING SERVICES AND GOODS (RESPONSE TO QUESTION B9).
Consulting Services
No. |
Description |
Cost Estimate incl. VAT (USD) |
Package No. |
Funding Source |
Selection Method (QCBS, CQS, ICS and etc.) |
Type of Contract |
Review by WB (Prior or Post) |
Issuance of REOI |
Issuance of RFP |
Proposal Submission |
Contract Signing |
Contract Start |
Contract Duration (months) |
1 |
Resettlement Policy Framework and Resettlement Action Plan |
200,000 |
FRM-PPTAF 01 |
PPTAF |
CQS |
LS |
Post |
9/2014 |
11/2014 |
11/2014 |
12/2014 |
12/2014 |
8 |
2 |
Environment impact assessment and environment management plan. |
298,000 |
FRM-PPTAF 02 |
PPTAF |
CQS |
LS |
Post |
9/2014 |
11/2014 |
12/2014 |
12/2014 |
12/2014 |
8 |
3 |
Review, update and amend the existing FSs of works items under Tham Luong – Ben Cat – Nuoc Len basin, consisting of: - FS of Tham Luong – Ben Cat – Nuoc Len main canal dredging and embankment. - FS of Nuoc Len Sluice Gate. - FS of Vam Thuat Sluice Gate. - FS of secondary canals connected to Tham Luong – Ben Cat – Nuoc Len canal. - FS of primary interceptor system. - FS of collecting stormwater and wastewater sewers systems in Go Vap district. |
200,000 |
FRM-PPTAF 03 |
PPTAF |
CQS |
LS |
Prior |
8/2014 |
10/2014 |
11/2014 |
11/2014 |
11/2014 |
5 |
4 |
Bidding documents preparation of civil works & equipments Vam Thuat tidal sluice gate. Survey, detailed design, cost estimate, bidding documents preparation of civil works & equipments for Nuoc Len tidal sluice gate. |
530,000 |
FRM -PPTAF 04 |
PPTAF |
QCBS |
LS |
Prior |
9/2014 |
11/2014 |
1/2015 |
4/2015 |
4/2015 |
5 |
5 |
Verification of detailed design and cost estimate of Nuoc Len tidal sluice gate. |
15,000 |
FRM-PPTAF 05 |
PPTAF |
CQS |
LS |
Post |
3/2015 |
5/2015 |
5/2015 |
6/2015 |
6/2015 |
3 |
6 |
Project Implementation Manual , Procurement Plan for initial 18 month. |
50,000 |
FRM-PPTAF 06 |
PPTAF |
CQS |
LS |
Post |
11/2014 |
1/2015 |
1/2015 |
2/2015 |
2/2015 |
6 |
7 |
Study retention ponds serving for flood prevention and drainage in Tham Luong – Ben Cat – Nuoc Len basin. |
145,000 |
FRM-PPTAF 07 |
PPTAF |
CQS |
LS |
Post |
8/2014 |
10/2014 |
11/2014 |
12/2014 |
12/2014 |
4 |
8 |
Individual Support for Procurement |
200,000 |
FRM-PPTAF 08 |
PPTAF |
IC |
Time-based |
Prior |
8/2014 |
8/2014 |
9/2014 |
9/2014 |
9/2014 |
15 |
Goods, Non-Consulting Services
No. |
Description |
Cost Estimate incl. VAT (USD) |
Package No. |
Funding Source |
Selection Method Shopping , Direct Contracting |
Type of Contract: SOE, PO, |
Review by WB (Prior or Post) |
Issuance of RFQ |
Bids Received |
Contract Signing |
Delivery Date |
1 |
Office equipment procurement for PMU of Works Construction serving for PPTAF sub-project. |
95,900 |
FRM-PPTAF 09 |
PPTAF |
Goods |
SOE |
Post |
8/2014 |
9/2014 |
9/2014 |
10/2014 |
|
Total: |
95,900 |
|
|
|
|
|
|
|
|
|